Project Location and Limits
This 1.5-mile pavement resurfacing project will be completed along Lake Street between Center Street and IL Route 83 (Barron Boulevard) in the Village of Grayslake.

Purpose and Funding
The Lake Street Resurfacing project is part of the Village of Grayslake’s continued initiative to improve the infrastructure throughout the community and is necessary to improve the driving surface and reduce future maintenance costs of the roadway.

This project will be funded by a combination of Surface Transportation Program (STP) funds provided by the Illinois Department of Transportation (IDOT) (80%) and local funds provided by the Village of Grayslake (20%).

View larger map

Project Scope & Schedule

Proposed Improvements
In general, the Lake Street Resurfacing project work will consist of asphalt pavement resurfacing. It is anticipated that this work will be completed in several phases which will typically include:

  • Minor storm sewer system upgrades.
  • Various concrete curb and gutter removal and replacement and sidewalk improvements.
  • Existing asphalt pavement surface removal.
  • Paving of new asphalt driving surface.
  • Landscape restoration, as needed.

What to Expect
The construction operations will likely create brief delays in travel, and motorists should allow extra time for trips through the area. We do not anticipate any street closures or detour routes. Access to all homes and businesses will be maintained, however, there will inevitably be delays encountered throughout the project. As with any construction project, there will occasionally be inconveniences you may experience, but the Village and Contractor are working together to minimize the disruptions and nuisances.

The project team thanks you in advance for your patience and cooperation this spring and summer. Motorists are urged to pay close attention to orange signs and flaggers in work zones, obey posted speed limits, avoid cell phone use, and be alert for construction workers and equipment.

Schedule
The Lake Street Resurfacing project is scheduled to begin on Wednesday, March 21, 2018, weather permitting, and we anticipate the project being completed by mid-August.

Project Update

The final punch list work is progressing along Lake Street

The contractor has completed the landscape restoration and the majority of the punch list work along Lake Street from Center Street to IL 83, and the roadway is now fully open. The landscape restoration will undergo a period of establishment after which the landscaping will be reviewed and approved or repaired as necessary. Motorists should …

The final punch list work is occurring along Lake Street

The contractor began landscape restoration and punch list work along Lake Street from Center Street to IL 83. Next week, weather permitting, the contractors plan to; Complete the final punch list work along Lake Street from Center Street to IL 83. Motorists should expect periodic lane closures along Lake Street as punch list work continues. …

Contact

Dan Strahan, P.E., CFM
Project Manager
Office: (847) 478-9700

Jennifer Beckman, P.E.
Resident Engineer
Cell: (312) 806-8727
Email: jbeckman@gha-engineers.com

Construction related questions or concerns should be directed to the project’s Resident Engineer, Jennifer Beckman, P.E.

 

Village of Grayslake
Public Works Department
(847) 223-8515

For other Village of Grayslake questions or concerns, please visit the Village’s online Request for Service System by clicking on the R4S logo below, or by phone at (847) 223-8515.