Storm Sewer Improvements are now Complete

As scheduled, the contractor completed the storm sewer installation and the saw cutting of the existing pavement along Lake Street, north of Washington Street this week.

Next week, weather permitting, the contractor plans to;

  • Continue excavation for the proposed curb & gutter along Lake Street, north of Washington Street
  • Begin to lower down the existing manhole frames in the roadway along Lake Street

Motorists should continue to expect daily lane closures along Lake Street as progress continues. Please be alert and aware of flaggers when traveling through the work zones.