Lake Street Roadway Improvements Continue as Scheduled

The contractor poured the proposed curb & gutter along Lake Street, north of Washington Street.

Next week, weather permitting, the contractors plan to;

  • Continue the removal and replacement of the proposed curb & gutter and sidewalk along Lake Street from Carol Lane to IL 83
  • Begin excavation and preparation for the bike path paving
  • Begin to lower down the existing manhole frames in the roadway

Motorists should expect daily lane closures along Lake Street as the improvements continue. As always, please be alert for construction workers and equipment.