Storm Sewer Improvements Continue

The contractor continued on schedule with the proposed storm sewer installation along Lake Street this week.

Next week, weather permitting, the contractor plans to continue with the storm sewer installation along Lake Street, north of Washington Street.

Motorists should expect daily lane closures along Lake Street as the improvements continue. As always, please be alert for construction workers and equipment.

Storm sewer work is progressing

Construction continued this week along Lake Street with the contractor progressing as scheduled on the proposed storm sewer installation.

Next week, weather permitting, the contractor plans to continue with the storm sewer installation along Lake Street, north of Washington Street.

Motorists should expect daily lane closures along Lake Street as the improvements continue. As always, please be alert when traveling through the work zones.

Construction Continues

Construction continued this week along Lake Street with the contractor beginning the proposed storm sewer installation as well as saw cutting the pavement.

Next week, weather permitting, the contractor plans to;

  • Continue with the storm sewer installation along Lake Street, north of Washington Street
  • Continue saw cutting the existing pavement for the proposed storm sewer improvements and roadway widening

Motorists should continue to expect daily lane closures along Lake Street as progress continues. As always, please be alert when traveling through the work zones.

Construction Begins

 

Construction began this week along Lake Street with the contractor setting up the traffic control signs and installing various erosion control measures.

Weather permitting, thcontractor anticipates beginning the storm sewer improvements along Lake Street, north of Washington Street. You will also see contractors bringing in equipment, saw cutting the pavement in various locations, and removing an existing guardrail. In order to complete this work, there will typically be daily lane closures along Lake Street, so please be aware of flaggers.

Welcome

On behalf of the Village of Grayslake, we would like to welcome you to the project website for the Lake Street Resurfacing project. This 1.5-mile construction project is intended to enhance the pavement’s riding surface and improve pedestrian access as well. Weather permitting, the construction is scheduled to begin next week. Please pay attention to the orange construction signs, and be alert for construction workers and equipment.

If you would like future project updates sent to you via email, please register at the bottom of this page by providing your email address in the appropriate box.

We thank you in advance for your patience and cooperation, and please pardon our dust during the improvements of this essential roadway through the Village of Grayslake.